The Naas Rd improvement scheme kicks off this weekend and no that does not mean that Newlands Cross is getting dug up just yet.
What is happening is that outbound on the Naas Rd will be closed over a few nights and weekends.
Outbound Works:
This Saturday from 7.30 Pm until Monday morning at 6AM works will be in place on the Naas Rd between Walkinstown Ave and Robinhood Rd
Then the following Saturday the 9th of March works will be in place in the same area from 7.30 PM to 6 AM on Monday the 11th.
There will also be works nightly between 7.30 PM and 6 AM from Monday the 11th to Friday the 15th.
Diversions via Walkinstown Ave and the Longmile Rd
Inbound Works:
These works take place between 7.30 PM to 6 AM from Monday the 18th to Friday the 22nd of March
Inbound diversions are via Kylemore Rd, Ballyferrmot, Sarsfield and Con Colbert Roads.