Thursday, January 16, 2014

Water Rehabilitation Works Update

Thursday 16th January 2014

Works will be taking place in the following locations this weekend  and next week.

Dublin 6W
Terenure Road North - Saturday 18th January 2014, working hours are 9am to 11pm. Works will be taking place at the junction of Terenure Road North and St. Enda’s Road. A 3 way Stop/Go system will be in operation at all times during the works.

Terenure Road North - Sunday 19th January 2014 , working hours are 9am to 11pm. Works will be taking place at the junction of Terenure Road North, Terenure Road East and Terenure Place. Lane restrictions will be in place

Dublin 12
Kimmage Road West - Saturday 18th and Sunday 19th January 2014, working hours are 9am to 11pm. Works will be taking place at the junction of Kimmage Road West and Whitehall Road. Traffic lights will be switched off and a 3 way Stop/Go system will be in operation at all times during the works.

Kimmage Road West - Monday 20th January to Friday 24th January, working hours are 10am to 4pm and then 7.30pm to 11pm. Works will be taking place along Kimmage Road West from the junction of Whitehall Road to the junction of Shelton Road and Lorcan O’Toole Road. A 2 way Stop/Go system will be in place at all times during the works.

2 way traffic will be maintained, however, there may be temporary Stop/Go boards in operation to facilitate the Grab lorry.

Dublin 2
Baggot Court & Pembroke Lane (Monday 20th January to Friday 24th January 2014)

Dublin 4
Sean Moore Road (Sat 18th Jan to Fri 24th Jan)

No comments:

Post a Comment